§755.525. Waiver of Requirements of Section 755.500  


Latest version.
  • The Commission shall grant a waiver of any requirements of Section 755.500 if the verified petition filed under that Section states that:

     

    a)         ITAC is unable to obtain the statement required under Section 755.500(a)(4) if the requirements are adhered to;

     

    b)         the reasons stated by the independent certified public accountant why the statement cannot be provided if the rule is adhered to; and

     

    c)         the alternate projections or underlying assumptions used by ITAC so that the independent certified public accountant is able to provide the statement required by Section 755.500(a)(4).

     

(Source:  Added at 17 Ill. Reg. 5594, effective March 31, 1993)