Illinois Administrative Code (Last Updated: March 27, 2024) |
TITLE44. GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT |
PART8. CHIEF PROCUREMENT OFFICER FOR THE CAPITAL DEVELOPMENT BOARD |
SUBPARTN. SELECTION OF CONSTRUCTION-RELATED PROFESSIONAL SERVICES, CONSTRUCTION MANAGEMENT SERVICES AND DESIGN-BUILD ENTITIES |
§8.3100. Design-Build Shortlist
-
a) Upon completion of the Phase 1 qualifications evaluation, CDB shall create a shortlist of no fewer than 2 and no more than 6 (or the maximum number noted in the RFP) of the most highly qualified DB entities and shall be reviewed by the CPO for conformance with the evaluation criteria in Section 8.3095.
b) CDB shall notify in writing the entities selected for the shortlist.
1) The notification shall commence the period for preparation of Phase 2 submittals as listed in the RFP.
2) CDB may extend the period beyond that listed in the RFP, at its discretion, by including the new deadline in the written notification.
c) All DB entities selected for Phase 2 evaluation shall be published on CDB's volume of the Procurement Bulletin after that determination.