§351.402. Decision of the Agency  


Latest version.
  • a)         After due consideration of the record, the Agency shall make a final decision on the proposed revision to the WQM Plan.

     

    1)         In making its decision, the Agency shall consider all facts and circumstances bearing upon the reasonableness of the request including, but not limited to, the environmental effects and the cost-effectiveness of achieving water quality goals.

     

    2)         The Agency's experience, technical competence and specialized knowledge may be utilized in the evaluation of the evidence.

     

    b)         The decision may grant or deny the proposed revision, in whole or in part, and may condition the revision upon the performance or completion of activities specified in the decision.

     

    c)         The final decision shall be in writing.  Copies of the decision shall be served on all parties personally or by registered or certified mail.