§218.445. Leaks: General Requirements  


Latest version.
  •             The owner or operator of a petroleum refinery shall:

     

    a)         Develop a monitoring program plan consistent with the provisions of Section 218.446;

     

    b)         Conduct a monitoring program consistent with the provisions of Section 218.447;

     

    c)         Record all leaking components which have a volatile organic material concentration exceeding 10,000 ppm consistent with the provisions of Section 218.448;

     

    d)         Identify each component consistent with the monitoring program plan submitted pursuant to Section 218.446;

     

    e)         Repair and retest the leaking components as soon as possible within 22 days after the leak is found, but no later than June 1 for the purposes of Section 218.447(a)(1), unless the leaking components cannot be repaired until the unit is shut down for turnaround; and

     

    f)         Report to the Agency consistent with the provisions of Section 218.449.

     

(Source:  Amended at 17 Ill. Reg. 16636, effective September 27, 1993)